Scope of work for ACB Servicing.-2No.
• Conduct site survey and verify existing infrastructure.
• Inspect the extinguisher chamber for damage and clean the required part.
• Rack out ACB.
• Removal of old grease and re-greasing the same with recommended grease.
• Clean & grease movable isolation contacts.
• Checking the reset mechanism, tripping the breaker through push button.
• Primary Injection Test
• Tripping the ACB manually through volumetric release.
• Inspect the ACB operating mechanism for damage and operational checking of for spring charge.
• Check mechanical & electrical interlocking system.
• Checking condition and alignment of jaw contact with cradle terminals.
• Checking condition of ACB wiring
Checking proper closing of all poles together.
• Checking working of anti-pumping device in case of EDO ACB.
• Checking scrapping earth alignment and condition of arc chutes.
• Checking U/V release coil.
• Setting of release as per the load
• Control wiring - checking for slack in terminal connection.
• Insulation Resistance Test.
• Testing and Commissioning.
• Submission of service & test reports for each ACB.
Scope of work for Capacitor Bank Servicing.-2No,
• Conduct site survey and verify existing infrastructure.
• Replacement of faulty components in the panel.
• Detailed Visual Inspection for any physical damage.
• Checking any faulty/burnt cables in the panels.
• Cleaning of busbar and its supports using appropriate CRC spray.
• Cleaning of the whole panel and verify the healthiness of Thermostat.
• Verify the operation of Exhaust fans in the panel.
• Tightness checks for busbars and all the components in the panel.
• Check & verify the program of Power Factor Regulator.
• Check & verify the operation of contactors through PF regulator manual operation/Test mode.
• Verify the healthiness of contactors.
• Insulation Resistance Test for Bus bar
• Record all data and Submission of service report.
Terms & Condition
No Subcontracting: In accordance to Jointly Owned Property Law No.6,2019, Notwithstanding anything in this Agreement, the vendor/contractor may not use any subcontractor to perform any of his obligations under this work order. Unless:
(a) Vendor has obtained the prior written consent of SAGA to the use of the subcontractor, and
(b) Vendor has entered into a separate written agreement with the subcontractor which requires the subcontractor to agree to and abide by all the terms and conditions of this Agreement.
The Community shall be deemed to be a third-party beneficiary of any such agreement between the vendor and a permitted subcontractor.
Notwithstanding the foregoing, the vendor shall not be relieved of any of its duties or obligations under this Agreement as a result of entering into a written agreement with a permitted subcontractor.
Payment will be done after 30 days work completion upon submitting the invoice along with work completion/service reports/warranty certificates.
APPLY NOW

SAGA International

The Haven Residences Jointly Owned Property
Residential3673+QR - Jumeirah Village - Dubai, Dubai, United Arab Emirates