1. Site Inspection, Design and Preparation
-
Conduct a detailed site inspection and verify the existing rooftop condition, dimensions, access routes, existing floor finishes, drainage points, electrical supply, and utility connections.
-
Prepare and submit a complete rooftop BBQ area layout, detailed technical drawings, material specifications, and 3D render design for management approval before commencing the works.
-
The contractor shall obtain all required authority approvals, permits, and NOCs applicable to the proposed works.
-
Protect existing waterproofing, drainage outlets, parapet walls, MEP installations, and adjacent finishes throughout the execution.
-
Carry out surface preparation, removal of loose or unsuitable finishes where required, and levelling of the substrate before installing new materials.
-
Any structural modification, penetration of the roof slab, or alteration to existing waterproofing shall be subject to prior inspection and written approval.
2. Outdoor Anti-Slip Flooring Works
-
Supply and install approximately 870 sq. ft. of outdoor-rated, anti-slip flooring, subject to final site measurement and approved layout.
-
Recommended material: 20 mm-thick outdoor porcelain paving tiles, suitable for rooftop and BBQ applications, with a textured, slip-resistant finish.
-
Recommended brands: RAK Ceramics
-
Select tiles with appropriate exterior slip resistance, UV stability, low water absorption, and resistance to temperature variations.
-
Prepare and level the substrate using a compatible exterior-grade levelling material, such as Mapei Planitop
-
Install tiles using an exterior-rated, flexible tile adhesive such as Mapei Keraflex Maxi S1 or SikaCeram-255
-
Apply suitable exterior-grade grout, such as Mapei Ultracolor Plus, in an approved colour.
-
Maintain existing drainage falls and ensure water flows freely towards the designated drainage points without ponding.
-
Provide neat tile cuts, edge finishing, movement joints, and perimeter detailing as required.
-
Do not drill or fix flooring systems through the existing waterproofing membrane without approved protection and detailing.
3. Outdoor Seating Arrangement
-
Supply and install weather-resistant outdoor seating, including benches, chairs, and tables as per the approved layout and final design.
-
Recommended materials: powder-coated aluminium frames with UV-resistant outdoor cushions, or high-quality teak hardwood suitable for exterior use.
-
Recommended brands: Kettal, Nardi, or Fermob outdoor furniture ranges,
-
Provide UV-resistant, water-resistant, and easy-to-clean upholstery suitable for outdoor use.
-
Use corrosion-resistant stainless-steel grade 316 or approved equivalent for exposed metal fixings where appropriate.
-
Ensure all seating is stable, properly assembled, and arranged to maintain safe circulation, accessibility, and adequate clearance around the BBQ equipment.
-
Provide sufficient seating capacity based on the approved design and available space.
4. Shading Structure / Canopy Installation
-
Supply and install an outdoor-rated shading structure or canopy to provide protection from direct sunlight over the designated seating and BBQ areas.
-
Submit structural details, shop drawings, fixing arrangements, wind-load calculations where required, and proposed material samples for approval.
-
Recommended structure: powder-coated aluminium framework with UV-resistant, weatherproof fabric canopy,
-
Recommended brands: KE Outdoor Design, Serge Ferrari for technical outdoor fabrics,
-
Use corrosion-resistant stainless-steel grade 316 fasteners and suitable weather-resistant brackets.
-
Select UV-resistant, fade-resistant, and moisture-resistant canopy materials appropriate for Dubai's outdoor climate.
-
Ensure the structure is stable and designed for the applicable wind loads and rooftop conditions.
-
Provide proper drainage arrangements where the canopy design requires them.
-
All anchoring and structural fixing methods shall be approved before installation and shall not compromise the existing roof waterproofing.
-
Obtain management and relevant authority approvals before installation.
5. BBQ Counter and Equipment
-
Supply and install a purpose-designed outdoor BBQ counter, including the worktop, supporting framework, storage cabinets, and BBQ equipment as per the approved layout.
-
Construct the counter using an outdoor-rated stainless-steel framework with moisture-resistant, non-combustible finishes in areas exposed to heat.
-
Recommended countertop material: granite or exterior-grade porcelain slab suitable for heat, UV exposure, and outdoor cleaning.
-
Provide outdoor-grade storage cabinets with corrosion-resistant hardware and suitable ventilation where required.
-
Supply and install a suitable BBQ grill, either gas-fired or electric, according to the approved design and available utilities.
-
Recommended BBQ brands: Weber,
-
The final BBQ model, dimensions, fuel type, heat output, and accessories shall be confirmed and approved before procurement.
-
Provide adequate heat-resistant clearances between the grill, counter, canopy, furniture, combustible materials, and adjacent building elements in accordance with the manufacturer's installation instructions.
-
For gas-fired equipment, provide approved gas piping, isolation valves, pressure regulation, leak testing, and required safety provisions, subject to authority approval.
-
For electric BBQ equipment, provide a dedicated electrical supply, appropriate circuit protection, earthing, and isolation arrangements.
-
Provide adequate ventilation and safe access for cleaning and maintenance.
-
Seal countertop joints and interfaces using suitable heat-resistant, exterior-grade sealant.
-
Test the installed BBQ equipment and demonstrate safe operation to the management representative.
6. Outdoor Lighting Works
-
Supply and install weatherproof LED lighting fixtures to illuminate the BBQ counter, seating areas, circulation routes, and decorative features.
-
Select luminaires with a minimum IP65 rating for exposed outdoor locations,
-
Recommended brands: Philips/ LEDVANCE
-
Use energy-efficient LED fixtures with a recommended colour temperature
-
Provide suitable illumination levels without glare or excessive light spill into neighbouring residential units.
-
Include decorative wall lights, pergola lights, and task lighting above the BBQ counter as shown in the approved design.
-
Use corrosion-resistant fittings and UV-resistant materials suitable for rooftop exposure.
-
Provide appropriate switching arrangements and separate control zones for seating, BBQ task lighting, and decorative lighting where required.
-
Submit product datasheets and lighting layout for approval before procurement.
7. Electrical Provisions
-
Inspect the existing electrical supply and verify the available capacity before connecting any new BBQ equipment or lighting circuits.
-
Supply and install appropriately sized cables, conduits, junction boxes, weatherproof sockets, isolators, and protective devices as required by the approved electrical design.
-
Recommended wiring accessories: Schneider Electric, ABB,
-
Use outdoor-rated sockets and enclosures with a suitable IP rating, typically IP55
-
Provide dedicated circuits for high-load BBQ equipment where required by the manufacturer's specifications and the approved electrical design.
-
Install suitable residual-current protection, circuit breakers, earthing, and bonding in accordance with applicable regulations.
-
Route cables through suitable UV-resistant and weatherproof conduits, with properly sealed entries and connections.
-
Ensure all electrical equipment is suitably located away from heat sources, water exposure, and BBQ operating zones.
-
Label circuits and isolators clearly and provide access for safe operation and maintenance.
-
All electrical installations shall be undertaken by qualified personnel and inspected, tested, and approved before energisation.
8. Aesthetic and Finishing Works
-
Enhance the overall appearance of the rooftop BBQ area in accordance with the approved design and render.
-
Supply and install coordinated outdoor finishes, decorative elements, and accessories suitable for the existing building architecture.
-
Recommended exterior-grade coating systems, where required, include Jotun Jotashield
-
Provide weather-resistant decorative screens, planter boxes, and suitable outdoor accessories where included in the approved design.
-
Recommended planter materials include powder-coated aluminium, UV-stabilised composite, or other durable outdoor-grade materials.
-
Supply suitable outdoor planting and decorative landscaping elements, where specified in the approved design, without obstructing drainage outlets or maintenance access.
-
Seal exposed joints and interfaces with an exterior-grade sealant such as Sika or Dow products suitable for the particular substrate and exposure.
-
Ensure all finishes are uniform, properly aligned, securely fixed, easy to maintain, and compatible with the rooftop environment.
-
Remove sharp edges, protrusions, loose fittings, and other potential safety hazards.
9. Testing, Inspection and Commissioning
-
Inspect all completed flooring, seating, shading, BBQ counter, equipment, and decorative installations for workmanship, stability, alignment, and safety.
-
Verify that flooring falls and drainage arrangements are functioning correctly and that no water ponding occurs.
-
Test all electrical circuits, sockets, isolators, protective devices, lighting fixtures, earthing, and bonding.
-
Verify the safe operation of the BBQ equipment and all associated utility connections.
-
Where gas equipment is installed, conduct the required gas leak tests and obtain the applicable inspection approvals.
-
Check canopy stability, fixing arrangements, and compliance with approved structural details.
-
Rectify all defects identified during inspection before final handover.
-
Submit applicable test reports, equipment manuals, warranties, and inspection certificates to the management representative.
10. Cleaning, Debris Removal and Handover
-
Remove all construction debris, packaging, surplus materials, and waste generated during the works.
-
Clean all flooring, countertops, furniture, lighting fixtures, and installed equipment.
-
Ensure the rooftop area, drainage outlets, and access routes are free from obstructions.
-
Provide as-built drawings reflecting the final installation, where applicable.
-
Submit approved material datasheets, equipment manuals, warranties, testing reports, and relevant authority approvals.
-
Demonstrate the operation of the installed equipment to the management team.
-
Hand over the completed rooftop BBQ area in a clean, safe, fully operational condition.
11. Recommended Material and Brand Schedule
|
Work item |
Recommended brand / material |
|---|---|
|
Outdoor porcelain flooring |
RAK Ceramics |
|
Tile adhesive |
Mapei / Sika |
|
Exterior tile grout |
Mapei Ultracolor Plus |
|
Outdoor furniture |
Nardi / Fermob / Kettal |
|
Canopy fabric |
Serge Ferrari |
|
Architectural shading |
Hunter Douglas / KE Outdoor Design |
|
BBQ grill |
Weber |
|
Outdoor LED lighting |
Philips / LEDVANCE |
|
Electrical accessories |
Schneider Electric / ABB |
|
Exterior paint |
Jotun |
|
Exterior sealant |
Sika / Dow |
All brands are recommendations for technical evaluation, not confirmed existing specifications or mandatory selections in the source PDF. Final products must be compatible with the application, available in the UAE
12. General Technical Requirements
-
All materials shall be new, genuine, outdoor-rated, and suitable for Dubai's heat, UV exposure, humidity, and environmental conditions.
-
The contractor shall submit technical datasheets, samples, shop drawings, and render designs for approval before ordering materials.
-
The contractor shall be responsible for obtaining the necessary authority approvals and permits for the proposed works.
-
Any structural modifications, waterproofing alterations, or additional utility connections shall require prior site inspection and written approval.
-
Existing waterproofing, roof drainage, fire-safety provisions, and building services shall be protected throughout the project.
-
All works shall comply with applicable Dubai regulations, relevant authority requirements, manufacturer recommendations, and approved drawings.
-
The contractor shall coordinate with management before starting disruptive works and shall maintain safe access to existing building services.
-
The contractor shall provide a recommended one-year warranty covering workmanship and supplied materials, subject to confirmation in the tender requirements and any longer manufacturer warranties.
-
Final quantities, specifications, seating capacity, canopy dimensions, BBQ model, electrical loads, and material selections shall be confirmed through the approved design and site measurements.
Important:
kindly visit the site confirm the scope and quantity and apply on the RFP. Variation not accepted.
Terms & Condition
1. Vendors are to use the Response Form provided and include all information requested by HOAM in relation to the RFP.
2. By submitting a Proposal the Vendor
accepts that it is bound by the RFP Process, Terms and Conditions (RFP-Terms)
a. examine the RFP and any
documents referenced in the RFP and any other information provided by HOAM
b. consider all risks,
contingencies and other circumstances relating to the delivery of the Requirements
and include adequate provision in its Proposal to manage such risks and contingencies.
c. document in its Proposal all
assumptions and qualifications made about the delivery of the Requirements,
including any assumption that HOAM or a third party will deliver any aspect of
the Requirements or incur any cost related to the delivery of the Requirements.
d. ensure that pricing information
is quoted in UAE dirhams (AED) inclusive of VAT.
e. satisfy itself as to the
correctness and sufficiency of its Proposal, including the proposed pricing and
the sustainability of the pricing.
f. There is no expectation or obligation for Vendors to submit Proposals in response to the RFP solely to remain on any prequalified or registered supplier list. Any Vendor on such a list will not be penalised for failure to submit a Proposal.
4. Proposals are to remain valid and open for acceptance by HOAM for the Offer Validity Period.
5. Each Vendor should satisfy itself as to the interpretation of the RFP. If there is any perceived ambiguity or uncertainty in the RFP document/s Vendors should seek clarification before the Deadline for Questions.
6. All requests for clarification must be made through the online system to HOAM’s Point of Contact. HOAM will endeavour to respond to requests in a timely manner, but not later than the deadline for HOAM to answer Vendors’ questions, if applicable.
7. If HOAM considers a request to
be of sufficient importance to all Vendors it may provide details of the
question and answer to other Vendors. In doing so HOAM may summarise the Vendor’s
question and will not disclose the Vendor’s identity. The question and answer
may be posted (updated on the system) and/or emailed to participating Vendors.
8. In submitting a request for clarification a Vendor is to indicate, in its request, any information that is commercially sensitive. HOAM will not publish such commercially sensitive information. However, HOAM may modify a request to eliminate such commercially sensitive information, and publish this and the answer where HOAM considers it of general significance to all Vendors.
9. Each Vendor is responsible for ensuring that its Proposal is received by HOAM on or before the Deadline for Proposals.
10. HOAM intends to rely on the Vendor’s
Proposal and all information provided by the Vendor (e.g. correspondence and
negotiations). In submitting a Proposal and communicating with HOAM each Vendor
should check that all information it provides to HOAM is:
a. true, accurate and complete,
and not misleading in any material respect
b. does not contain Intellectual Property that will breach a third party’s rights.
11. Where HOAM requires the Proposal to be delivered in hard and soft copies, the Vendor is responsible for ensuring that both the hard and soft copies are identical.
12. HOAM will convene an evaluation panel comprising members chosen for their relevant expertise and experience. In addition, HOAM may invite independent advisors to evaluate any Proposal, or any aspect of any Proposal.
13. Each Vendor authorises HOAM to collect additional information, and to use that information as part of its evaluation of the Vendor’s Proposal.
14. Each Vendor is to ensure that all referees listed in support of its Proposal agree to provide a reference.
15. To facilitate discussions between HOAM and third parties each Vendor waives any confidentiality obligations that would otherwise apply to information held by a third party.
16. HOAM may, at any time, request from any Vendor clarification of its Proposal as well as additional information about any aspect of its Proposal. HOAM is not required to request the same clarification or information from each Vendor.
17. The Vendor must provide the clarification or additional information in the format requested. Vendors will endeavour to respond to requests in a timely manner. HOAM may take such clarification or additional information into account in evaluating the Proposal.
18. Where a Vendor fails to respond adequately or within a reasonable time to a request for clarification or additional information, HOAM may cease evaluating the Vendor’s Proposal and may eliminate the Proposal from the RFP process.
19. HOAM will base its initial evaluation on the Proposals submitted in response to the RFP. HOAM may adjust its evaluation of a Proposal following consideration of any clarification or additional information.
20. In deciding which Vendor/s to
shortlist HOAM will take into account the results of the evaluations of each
Proposal and the following additional information:
a. each Vendor’s understanding of
the Requirements, capability to fully deliver the Requirements and willingness
to meet the terms and conditions of the Proposed Contract
b. except where the price is the only criterion, the best value-for-money over the whole of-life of the goods or services.
21. In deciding which Vendor/s, to
shortlist HOAM may take into account any of the following additional
information:
a. the results from reference
checks, site visits, product testing and any other due diligence
b. the ease of contracting with a Vendor
based on that Vendor’s feedback on the Proposed Contract (where these do not
form part of the weighted criteria)
c. any matter that materially
impacts on HOAM’s trust and confidence in the Vendor
d. any other relevant information that HOAM may have in its possession.
22. HOAM will advise Vendors if they have been shortlisted or not. Being shortlisted does not constitute acceptance by HOAM of the Vendor’s Proposal, or imply or create any obligation on HOAM to enter into negotiations with, or award a Contract for delivery of the Requirements to any shortlisted Vendor/s. At this stage in the RFP process HOAM will not make public the names of the shortlisted Vendors.
23. HOAM may invite a Vendor to enter into negotiations with a view to contract. Where the outcome is unsatisfactory HOAM may discontinue negotiations with a Vendor and may then initiate negotiations with another Vendor.
24. HOAM may initiate concurrent negotiations with more than one Vendor. In concurrent negotiations HOAM will treat each Vendor fairly.
25. Each Vendor agrees that any
legally binding contract entered into between the Successful Vendor and HOAM
will be essentially in the form of the Proposed Contract.
1. All enquiries regarding the RFP must be directed to HOAM’s Point of Contact.
2. Vendors must not directly or indirectly approach any representative of HOAM, or any other person, to solicit information concerning any aspect of the RFP.
3. Only the Point of Contact, and any authorised person of HOAM, are authorised to communicate with Vendors regarding any aspect of the RFP. HOAM will not be bound by any statement made by any other person.
4. HOAM may change the Point of
Contact at any time. This notification may be posted on the system.
Where a Vendor has an existing contract with HOAM then business as usual communications, for the purpose of managing delivery of that contract, will continue using the usual contacts. Vendors must not use business as usual contacts to lobby HOAM, solicit information or discuss aspects of the RFP.
6. Each Vendor must accept and adhere to the Conflict of Interest declaration in the Response Form and must immediately inform HOAM should a Conflict of Interest arise during the RFP process. A material Conflict of Interest may result in the Vendor being disqualified from participating further in the RFP.
7. Vendors must not attempt to influence or provide any form of personal inducement, reward or benefit to any representative of HOAM in relation to the RFP.
8. A Vendor who attempts to do anything prohibited may be disqualified from participating further in the RFP process.
9. HOAM reserves the right to require additional declarations, or other evidence from a Vendor, or any other person, throughout the RFP process to ensure probity of the RFP process.
10. Vendors must not engage in collusive, deceptive or improper conduct in the preparation of their Proposals or other submissions or in any discussions or negotiations with HOAM. Such behaviour will result in the Vendor being disqualified from participating further in the RFP process. In submitting a Proposal the Vendor warrants that its Proposal has not been prepared in collusion with a Competitor.
11. HOAM reserves the right, at its discretion, to report suspected collusive or anticompetitive conduct by Vendors to the appropriate authority and to give that authority all relevant information including a Vendor’s Proposal.
12. HOAM and Vendor will each take reasonable steps to protect Confidential Information and, without limiting any confidentiality undertaking agreed between them, will not disclose Confidential Information to a third party without the other’s prior written consent.
13. HOAM and Vendor may each disclose Confidential Information to any person who is directly involved in the RFP process on its behalf, such as officers, employees, consultants, contractors, professional advisors, evaluation panel members, partners, principals or directors, but only for the purpose of participating in the RFP.
14. Vendors acknowledge that by law, HOAM will not be in breach of its obligations if Confidential Information is disclosed by HOAM to the appropriate authority because of suspected collusive or anticompetitive tendering behaviour. Where HOAM receives a request that relates to a Vendor’s Confidential Information HOAM will consult with the Vendor and may ask the Vendor to explain why the information is considered by the Vendor to be confidential or commercially sensitive.
15. For the duration of the RFP, to the date of the announcement of the Successful Vendor, or the end of the RFP process, the Vendor agrees to keep the RFP strictly confidential and not make any public statement to any third party in relation to any aspect of the RFP, the RFP process or the award of any Contract without HOAM’s prior written consent.
16. A Vendor may disclose RFP information to any person but only for the purpose of participating in the RFP. The Vendor must take reasonable steps to ensure that such recipients do not disclose Confidential Information to any other person or use Confidential Information for any purpose other than responding to the RFP.
17. Each Vendor will meet its own costs associated with the preparation and presentation of its Proposal and any negotiations.
Ownership
of documents
18. The RFP and its contents remain the property of HOAM. All Intellectual Property rights in the RFP remain the property of HOAM or its licensors. HOAM may request the immediate return or destruction of any or all RFP documents and any copies. Vendors must comply with any such request in a timely manner.
19. All documents forming the Proposal will, when delivered to HOAM, become the property of HOAM. Proposals will not be returned to Vendors at the end of the RFP process.
20. Ownership of Intellectual Property rights in the Proposal remain the property of the Vendor or its licensors. However, the Vendor grants to HOAM a non-exclusive, non-transferable, perpetual licence to retain, use, copy and disclose the information contained in the Proposal for any purpose related to the RFP process.
No binding legal relations
21. Neither the RFP, nor the RFP process creates a process contract or any legal relationship between HOAM and any Vendor, except in respect of:
a. the Vendor’s declaration in its
Proposal
b. the Offer Validity Period
c. the Vendor’s statements,
representations and/or warranties in its Proposal and in its correspondence and
negotiations with HOAM.
d. no legal relationship is formed
between HOAM and any Vendor unless and until a contract is entered into between
those parties.
Elimination
22. HOAM may exclude a Vendor from
participating in the RFP if HOAM has evidence of any of the following, and is
considered by HOAM to be material to the RFP:
a. the Vendor has failed to
provide all information requested, or in the correct format, or materially
breached a term or condition of the RFP
b. the Proposal contains a
material error, omission or inaccuracy
c. the Vendor is in bankruptcy,
receivership or liquidation
d. the Vendor has made a false
declaration
e. there is a serious performance
issue in a historic or current contract delivered by the Vendor
f. the Vendor has been convicted
of a serious crime or offence
g. there is professional
misconduct or an act or omission on the part of the Vendor which adversely
reflects on the integrity of the Vendor
1. Despite any other provision in
the RFP HOAM may, on giving due notice to Vendors:
a. amend, suspend, cancel and/or
re-issue the RFP, or any part of the RFP
b. make any material change to the
RFP (including any change to the timeline, Requirements or Evaluation Approach).
a. in exceptional circumstances,
accept a late Proposal where it considers that there is no material prejudice
to other Vendors. HOAM will not accept a late Proposal if it considers that
there is risk of collusion on the part of a Vendor, or the Vendor may have
knowledge of the content of any other Proposal
b. in exceptional circumstances,
answer a question submitted after the Deadline for Questions, if applicable
c. accept or reject any Proposal,
or part of a Proposal
d. accept or reject any
non-compliant, non-conforming or alternative Proposal
e. decide not to accept the lowest
priced conforming Proposal unless this is stated as the Evaluation Approach
f. decide not to enter into a
Contract with any Vendor
g. liaise or negotiate with any Vendor
without disclosing this to, or doing the same with, any other Vendor
h. provide or withhold from any Vendor
information in relation to any question arising in relation to the RFP.
Information will usually only be withheld if it is deemed unnecessary, is
commercially sensitive to a Vendor, is inappropriate to supply at the time of
the request or cannot be released for legal reasons
i. amend the Proposed Contract at
any time, including during negotiations with a shortlisted Vendor
j. waive irregularities or
requirements in or during the RFP process where it considers it appropriate and
reasonable to do so.
3. HOAM may request that a Vendor/s
agrees to HOAM:
a. selecting any individual
element/s of the Requirements that is offered in a Proposal and capable of
being delivered separately, unless the Proposal specifically states that the
Proposal, or elements of the Proposal, are to be taken collectively
b. selecting two or more Vendors
to deliver the Requirements as a joint venture or consortium.
Law of
the Emirate of Dubai
4. The laws of The Emirate of
Dubai shall govern the RFP and each Vendor agrees to submit to the exclusive
jurisdiction of the Emirate of Dubai courts in respect of any dispute concerning
the RFP or the RFP process.
HOAM will not be liable in
contract, tort, equity, or in any other way whatsoever for any direct or
indirect damage, loss or cost incurred by any Vendor or any other person in
respect of the RFP process.
2. Nothing contained or implied in the RFP, or RFP process, or any other communication by HOAM to any Vendor shall be construed as legal, financial, or other advice. HOAM has endeavored to ensure the integrity of such information. However, it has not been independently verified and may not be updated.
3. HOAM has issued the RFP with the intent of purchasing the goods or services described in the Requirements. The term HOAM (Highrise Owners Association Management LLC) includes its officers, employees, contractors, consultants, agents and representatives.
HOAM- Highrise Owners Association Management
Pantheon Boulevard
ResidentialPantheon Boulevard, Jumeirah Village Circle, Dubai, United Arab Emirates