Supply and Replacement of New VFD

Break Down
Posted On: November 17, 2025
Closing On: November 21, 2025
JOB REFERENCE:
JB007-25-04709

Location: Mechanical Floor - Chilled Water Pump No.1


1. Removal of Existing Faulty VFD (1 No.)

  • Safely isolate electrical supply to the existing Variable Frequency Drive (VFD).
  • Disconnect all power and control wiring from the faulty unit.
  • Carefully remove the existing VFD from the panel/mounting arrangement.
  • Hand over the removed VFD as per client instructions.

 

2. Supply & Installation of New 30 kW VFD (ABB ACH580) – 1 No.

  • Supply new 30 kW ABB ACH580 HVAC series VFD with appropriate ratings and specifications.
  • Inspect mounting space and prepare the panel for installation.
  • Install the VFD securely on the existing or modified mounting arrangement.
  • Ensure proper ventilation, spacing, and safety clearances.

 

3. Control & Power Wiring Modification for New VFD (1 No.)

  • Review existing wiring layout and update as per new VFD requirements.
  • Modify control wiring (I/O terminals, communication, interlocks, feedback signals, etc.).
  • Upgrade or alter power wiring including:
    • Supply input cables
    • Motor output connections
    • Earthing conductor connections
  • Ensure all wiring meets electrical standards and ABB installation guidelines.

 

4. Programming & Configuration of VFD as per Site Logic (1 No.)

  • Program the ABB ACH580 VFD according to site-specific functional logic.
  • Configure parameters such as:
    • Motor data
    • Start/stop logic
    • Speed reference
    • Protection limits
    • Communication settings
  • Conduct verification of interlocks and safety features.

 

5. Testing & Commissioning

  • Perform pre-commissioning checks (insulation, continuity, power supply).
  • Energize the VFD and perform functional testing with motor.
  • Verify:
    • Correct rotation
    • Speed control
    • Load response
    • Trip conditions and safety functions
  • Conduct performance trials under actual operating conditions.
  • Handover commissioning report to the Building Management.

 

Terms & Condition

No Subcontracting: In accordance to Jointly Owned Property Law No.6,2019, Notwithstanding anything in this Agreement, the vendor/contractor may not use any subcontractor to perform any of his obligations under this work order. Unless: 

(a) Vendor has obtained the prior written consent of SAGA to the use of the subcontractor, and 

(b) Vendor has entered into a separate written agreement with the subcontractor which requires the subcontractor to agree to and abide by all the terms and conditions of this Agreement. 

The Community shall be deemed to be a third-party beneficiary of any such agreement between the vendor and a permitted subcontractor. 

Notwithstanding the foregoing, the vendor shall not be relieved of any of its duties or obligations under this Agreement as a result of entering into a written agreement with a permitted subcontractor.
APPLY NOW
SAGA International Owners Association Management Services LLC
SAGA International Owners Association Management Services LLC
Mazaya Business Avenue BB1 Jointly Owned Property
Mazaya Business Avenue BB1 Jointly Owned Property
Commercial

Mazaya Business Avenue BB1 Jumeirah Lakes Tower, Dubai, United Arab Emirates

Share