A.
A. Site Survey &
Assessment
•
Conduct a detailed site inspection to understand the work requirements (lift -
interior walls only).
B.
B. Safety Measures &
Mobilization
• Implement necessary HSE protocols,
including PPE and Lockout/Tagout (LOTO).
• Cover all floors and sensitive areas with
protective mats.
• Coordinate with building management for
safe execution.
C.
C. The contractor shall be
responsible for:
• Surface preparation, cleaning and
leveling to ensure proper adhesion of the wrapping film.
• Supply of premium quality architectural
wrapping film (finish: metallic and water resistant design, Client suggested
material TBD, code - S140).
• Installation of wrapping film to elevator
interior walls only (excluding ceiling, floor and fixtures unless specified).
• Finishing, trimming and ensuring seamless
joints with no visible air bubbles or wrinkles.
• Handover after final inspection and
submit the warranty certificate along with completion report.
D.
D. Compliance & Safety
• Elevators under wrapping works must be
locked/tagged out and not used by residents/tenants during installation.
• Workers must use proper PPE (safety
gloves, masks, safety shoes, etc.).
• Materials used must be low-odor,
non-toxic, and fire-rated to avoid risk to building occupants.
• Work area to be cordoned off with safety
signage and barriers.
• Compliance with Dubai Municipality and
building HSE requirements.
E.
E. Material Specifications
and Deliverables
•
Type: Premium architectural wrapping film.
• Finish: Metal-look / waterproof (Design
to be approved from client prior to installation).
• Durability: Scratch-resistant,
easy-to-clean, fire-rated where applicable.
• Warranty: Minimum 5 years (60 months) to
be provided.
• Warranty certificates and material
datasheets.
Note:
• Contractor to do detailed site survey during the mandatory
site visit.
• Proposal shall consist of all the material requirements
and measurements. Any variation requests after issuing LPO or thereafter will
not be accepted by client.
• Any services, item of work or small detail not
specifically mentioned but inferred and necessary for the satisfactory
operation of the system or installation shall be provided by the Contractor
without any additional cost to the Client.
• Contractor will arrange their own materials/equipment when
needed for carrying out the work.
• Contractor is responsible to use their own tools
(third-party certified) and access equipment whenever needed for satisfactory
completion of job.
• It is the responsibility of the contractor to follow all
applicable Dubai Municipality and UAE regulations.
For any site assistance, contact SUHAIL AVULAN at 050 625 8292
Terms & Condition

SAGA International Owners Association Management Services LLC

Dubai Gate 2 Jointly Owned Property
ResidentialDubai Gate 2 Cluster A Jumeirah Lakes Tower, Dubai, United Arab Emirates