Chiller 2 & 3 - Rectification Works
ServicesJOB REFERENCE:
JB007-25-04825
Ch-2 Circuit-A:
Stator Rewinding
Unit Model: 30GX-328
Serial No: 12Y616030
Scope of Work:
• Check the general operation and log or report the
condition
• Lock-out the chiller.
• Isolate the chiller from electrical source.
• Open the stator of compressor A1 for complete rewinding.
• Take out the rotor for repair.
• Fix back the rotor and stator after repair.
• Supply & replacement of compressor contactor.
• Supply & replacement of SCPM Board
• Supply & replacement of filters.
• Charge refrigerant top-up.
• Charge fresh oil.
• Start-up the chiller and observe the operation.
• Log parameters and hand over the chiller to the customer.
CH-2 Circuit-B:
CH2 Circuit-B:
Replacement of Compressors
Unit Model: 30GX-328
Serial No: 12Y616030
Scope of work:
• Check the general operation and log or report the
condition
• Lock-out the chiller & disconnect the compressor from
electrical termination.
• Recover the refrigerant from circuit 2.
• Supply & replacement of 1 no’s compressor (2B).
• Supply & replacement of 6 no’s compressor fuses
(160A).
• Supply & replacement of SCPM Board.
• Supply & replacement of internal & external oil
filters (2 times).
• Supply & replacement of DGT sensors with cables.
• Supply & replacement of compressor oil 40L (2 times).
• Supply & replacement of drier cores (2 times).
• Supply & replacement of O-rings.
• Supply & replacement of compressor contactors.
• Pressure test with nitrogen.
• Evacuate the system as per standards.
• Charge new refrigerant.
• Start-up the chiller and observe the operation.
• Log parameters and hand over the chiller to the customer
Ch-3: Leak
Repair & Replacement of Compressor Contactor
Unit Model: 30GX-328
Serial No: 12Y616029
Scope of Work:
• Check the general operation and log or report the
condition
• Lock-out the chiller.
• Isolate the chiller from electrical source.
• Pressure test the circuit-A with nitrogen for leak and
repair.
• Evacuate the system as per standards.
• Charge fresh refrigerant and oil on circuit-A.
• Supply & replacement of compressor contactor on
circuit-B.
• Supply & replacement of internal & external oil
filters on circuit-A.
• Supply & replacement of drier cores on circuit-A.
• Supply & replacement of DGT sensor on circuit-A.
• Supply & replacement of oil solenoid valve on
circuit-A.
• Start-up the chiller and observe the operation.
• Log parameters and hand over the chiller to the customer.